How to Prepare for CORENET X BIM Submissions
Published on
• Updated on

How to Prepare for CORENET X BIM Submissions

Key Takeaways

  • Prepare coordinated BIM models with the required IFC+SG data rather than relying on native Revit, ArchiCAD, or MicroStation files alone.
  • Check the requirements for the current gateway before filling parameters that agencies only need at a later stage.
  • Let the responsible consultants resolve design decisions, such as a door's fire rating, before coordinators update the model data.
  • Review the federated models before submission because outstanding information in one discipline can delay the entire gateway.

Preparing Building Information Modelling (BIM) models for CORENET X means coordinating the discipline models, exporting the required IFC+SG information, checking the parameters for the current gateway, and resolving design decisions with the responsible consultants. IFC+SG is Singapore's extension of the open Industry Foundation Classes (IFC) schema.

At Bimeco, we've delivered 845 projects since 2005, and we've seen how much time can go into preparing information that isn't needed yet. A team may spend days filling IFC+SG parameters for later gateways while the BIM coordinator waits for consultants to resolve missing design decisions.

For more on the submission framework, see our CORENET X requirements guide and CORENET X vs CORENET 2.0 comparison.

What Is CORENET X

CORENET X is Singapore's integrated regulatory submission platform for building works. It brings agencies including the Building and Construction Authority (BCA), Urban Redevelopment Authority (URA), Singapore Civil Defence Force (SCDF), Public Utilities Board (PUB), and National Environment Agency (NEA) into a coordinated review process.

The process has three main gateways: Design, Construction, and Completion. There's also an optional Piling Gateway for qualifying projects that need to begin piling works before Construction Gateway approval. Eligible projects may follow the Direct Submission Process, subject to the applicable criteria.

From 1 October 2026, mandatory CORENET X Gateway submissions apply to qualifying new projects involving:

  • New buildings with at least 5,000 m² total gross floor area (GFA).
  • Additions or extensions creating at least 5,000 m² additional GFA.
  • Major addition and alteration (A&A) works affecting or replacing at least 5,000 m² GFA.

Projects below the threshold can continue under CORENET 2.0 for now. Transitional arrangements also apply to projects that commenced relevant submissions before the cut-off. Check the July 2026 implementation circular before deciding which route applies.

For projects requiring IFC+SG submissions, the architectural, structural, and mechanical and electrical (M&E) models must be coordinated before agency review. Each discipline needs to supply the model information required at that gateway.

BIM Modelling for CORENET X

ISO 19650 information management
ISO 19650 information management

I'd start with the discipline models themselves. Exporting to IFC+SG won't resolve clashes, inconsistent coordinates, or missing information that should have been addressed during modelling.

The architect and engineering consultants should agree on modelling standards early, including the Level of Development (LOD) appropriate to each element and gateway. LOD 350 may be appropriate where coordination requires it; it should not be treated as a blanket submission requirement. Before preparing the export, check:

  • Clash detection: Are architectural, structural, and M&E elements properly coordinated?
  • Geo-coordination: Are the discipline models using consistent project coordinates?
  • Submission information: Have consultants included the data needed for the current gateway?

ISO 19650 isn't mandatory for CORENET X, although its Work in Progress (WIP), Shared, and Published states provide a useful framework for managing model exchanges. Our BIM LOD guide explains the development levels in more detail.

Consultants may use Autodesk Revit, Graphisoft ArchiCAD, Bentley MicroStation, or other authoring software. These applications produce proprietary files, whereas submissions requiring IFC+SG need data structured in the open schema.

Exporting alone doesn't establish compliance. Property mapping and classification still need attention, preferably while the models are being developed rather than after export.

IFC+SG Validation for CORENET X

Parametric validation report showing missing IFC+SG values on doors, flagged by agency
Parametric validation report showing missing IFC+SG values on doors, flagged by agency

BCA's industry mapping file specifies IFC entities, property sets, required properties, and controlled values. Read it alongside the Code of Practice to identify what the current gateway and relevant agencies require. On a large project, checking those properties manually across hundreds or thousands of elements is tedious and error-prone.

We use the Bimeco Validator to check those parameters. It reports missing information, incorrect values, and classification gaps, with results organised by discipline, storey, property, and value. Consultants can review the report in a browser without opening the native BIM authoring software.

Passing IFC+SG parameter validation doesn't guarantee regulatory approval. The design must still satisfy the relevant agency requirements.

Check which Code of Practice edition applies before configuring the checks. From 1 January 2027, new gateway submissions must adopt Edition 4.0. Ongoing submissions under review, including resubmissions following Written Directions, may continue using their existing edition until approval for that gateway. The official transition guidance also covers amendment and structural submissions.

Filter by Gateway

SelfClosing parameter on door elements tagged as an SCDF requirement
SelfClosing parameter on door elements tagged as an SCDF requirement

I wouldn't run a Design Gateway model against the entire IFC+SG parameter list. That can produce hundreds of missing values that aren't required until Construction or Completion Gateway.

We filter the checks by gateway and agency, then work through the relevant failures. This keeps the team focused on information needed for the current submission.

For example, during fire compartmentation review, SCDF needs information about whether certain doors are self-closing. The Bimeco Validator identifies the SelfClosing parameter as an SCDF requirement, allowing consultants to locate the relevant entries without sorting through unrelated properties.

Bulk Editing

Bulk filling 38 missing ThermalTransmittance values in the Bimeco Validator's Excel-like interface
Bulk filling 38 missing ThermalTransmittance values in the Bimeco Validator's Excel-like interface

After filtering the results, you'll often find the same missing property across multiple elements. A model might have two hundred doors requiring the same parameter to be populated.

The Bimeco Validator has an Excel-like interface for making these corrections in bulk. The screenshot above shows 38 missing ThermalTransmittance values being filled together rather than editing each element separately.

A shared missing property doesn't mean every element should receive the same value. Confirm the consultant's decision and group only the elements to which that value applies before making a bulk correction.

Fixing IFC+SG Validation Issues

Editing element status (Proposed, Existing, Demolished) directly in the browser, with fire rating and material visible per element
Editing element status (Proposed, Existing, Demolished) directly in the browser, with fire rating and material visible per element

Fixing BIM model issues used to be treated as a modeller's job. With IFC+SG, consultants can and should resolve the values that require their design input. A missing parameter isn't always a modelling problem.

A door's fire rating is one example. The coordinator can identify the missing parameter, but the responsible consultant determines the rating. Passing the issue through the coordinator before getting the consultant's answer adds an unnecessary round of work.

Once those decisions have been made, the appointed BIM coordinators can work through the remaining model-data corrections. Keep the decision attached to the affected elements so the team can check that the recorded values match what the consultant specified.

Revit Plugin for IFC+SG Sync

Bimeco Validator on the Autodesk Marketplace: plugin for round-trip IFC-to-Revit synchronisation
Bimeco Validator on the Autodesk Marketplace: plugin for round-trip IFC-to-Revit synchronisation

Correcting the IFC+SG data creates another problem if those changes never make it back into the native BIM model. You could have a validated value in the IFC file while Revit still contains the previous information.

Bimeco provides a Revit plugin on the Autodesk Marketplace, compatible with Revit 2025, 2026, and 2027. It detects changes made to IFC files and supports applying them back to the source Revit project, with change reports for review before updates are applied.

The Validator also maintains revision history and an audit trail. When a team returns for A&A works, it can refer to the previously validated model to understand the recorded element status. The team still needs to check that those records reflect the building's current condition.

Managing CORENET X Submission Readiness and Resubmissions

Inviting project stakeholders to a federated model review
Inviting project stakeholders to a federated model review

One discipline can hold up a gateway even when the others are ready. The structural model might have passed its internal checks while the M&E model still contains missing mandatory parameters.

We'd rather catch those issues during a pre-submission review than wait for a Written Direction.

The Bimeco Validator allows project stakeholders to collaborate on federated models. During preparation, divide the work between the people responsible for each part:

  • Project Coordinator: Often the architect, invites stakeholders by email and coordinates the discipline models.
  • Consultants: Validate their respective models and resolve issues within their design responsibilities.
  • BIM coordinators: Address the remaining model-data corrections and help prepare the models for another coordinated check.

After the outstanding issues have been resolved, review the federated models again before submission or resubmission. Separate discipline files still form part of a coordinated submission package; federation does not remove each Qualified Person's responsibility for their work.

Written Directions can require further corrections and another submission cycle. The official submission workflow describes agency comments in BIM Collaboration Format (BCF) files and fee top-ups in specific circumstances. Internal coordination won't eliminate every regulatory comment, but it can prevent missing model information from becoming an avoidable resubmission.

IFC+SG Training for Project Teams

A validation report can identify a missing parameter. Knowing what belongs in that field is a different matter, especially when it depends on the design.

Include consultants in IFC+SG training, not just BIM coordinators. Consultants need to understand the properties they must provide, while modellers need to know how those values are represented in Revit and mapped to IFC+SG.

The Advanced IFC+SG course at Ace Industrial Academy (AIA) covers Revit export configuration, coordination, parameter workflows, validation, and failure resolution. Choose training that helps the team trace a reported issue back to its source and recognise when a consultant's decision is needed.

PSG Grant for CORENET X Compliance

BCA's Built Environment Productivity Solutions Grant (PSG) supports eligible local small and medium-sized enterprises (SMEs) adopting pre-approved digital solutions under the Built Environment Industry Digital Plan.

Under the current funding terms, firms can receive up to 50% co-funding of qualifying digital-solution costs, capped at S$50,000 per firm over the five-year tranche from 1 April 2026 to 31 March 2031. Apply before confirming a contract or making any payment or deposit. A tool's relevance to CORENET X does not establish grant eligibility; check the specific package's approval status.

BCA has announced a planned transition of the Built Environment PSG to EDGE in December 2026. Check the current BCA funding notice before applying. Our PSG grant guide covers the eligibility requirements and application process.

Preparing for Your Next CORENET X Submission

Before submitting, I'd want to know that the discipline models are coordinated, the mandatory IFC+SG parameters for the current gateway have been checked, and the consultants have resolved the design information they're responsible for.

The Validator helps us find and correct missing model data, but it doesn't replace the consultants' decisions.

If your team needs help preparing for CORENET X, Bimeco's CORENET X BIM submission services provide IFC+SG validation and BIM coordination support to help you prepare your models for submission.

Frequently Asked Questions

No. From 1 October 2026, CORENET X Gateway Processes are mandatory for qualifying new projects with gross floor area (GFA) of at least 5,000 m². Projects below that threshold can continue under CORENET 2.0 for now or adopt CORENET X voluntarily. IFC+SG extends Industry Foundation Classes (IFC) for Singapore’s Building Information Modelling (BIM) submissions; other permitted formats may apply where IFC+SG is not required. See our CORENET X requirements guide for the scope and transitional arrangements.
Revit parameters do not always transfer into the exported Industry Foundation Classes (IFC) file. Check the property-set export settings, parameter mapping, and IFC classifications against the current IFC+SG requirements. The Bimeco Validator can identify missing properties, while the official authoring-tool resources explain the export setup. Correct the source mapping and check a fresh export so the same properties are not lost during the next model exchange.
Yes. Project teams can include separate IFC+SG models by discipline or building block within a coordinated submission package. IFC+SG extends the Industry Foundation Classes (IFC) schema for Singapore. Separate files do not mean independent, uncoordinated submissions. Architectural, structural, and mechanical and electrical (M&E) models must be properly geo-referenced and coordinated for federation. Check that the models align and use consistent project coordinates before submission. Qualified Persons remain responsible for coordination and compliance with the applicable requirements.
Written Directions for Building Information Modelling (BIM) submissions include BIM Collaboration Format (BCF) files containing agency comments. Open the BCF in compatible software, review the affected model elements, coordinate the corrections, and submit updated files. Do not reuse outdated models or plans. Fee top-ups may be required in certain cases, such as incorrect form inputs or a change from lodgement to a processed submission; a Written Direction does not automatically mean paying every submission fee again.
The Building and Construction Authority (BCA) Built Environment Productivity Solutions Grant (PSG) provides eligible local small and medium-sized enterprises (SMEs) with up to 50% co-funding for pre-approved digital solutions, capped at S$50,000 per firm over the five-year tranche. Funding depends on the specific software package’s approval status. Check the current list before applying and submit the application before confirming a contract or making any payment or deposit. Our PSG grant guide explains the process.